INSTALLATION GUIDELINES
It is essential that the compressor is installed properly. This will improve the reliability of your compressor, prevent breakdown, and ensure high uptime. Deep Pneumatics Installation & Maintenance Guidelines is a quick guide on how to design your compressor room or workplace. This helps you to prepare for the installation of a compressor even before the unit has arrived at your site. The unit is ready to be installed and commissioned the moment it arrives at your site. No modifications will be required as you would have already taken into consideration all factors while designing the compressor workplace.
Please go through the guideline before designing a compressor room or installing our compressor. In case you need any further assistance please contact our nearest dealer you may contact on our customer care No. +91-79-22803684.

GUIDELINES FOR FASTER AND EFFECTIVE INSTALLATION

GUIDELINES FOR COMMISSIONING/INSTALLATION OF INDUSTRIAL AIR COMPRESSORS

RECOMMENDED INCOMING CABLE SIZE & OVER LOAD SETTING
MOTOR RATING | INCOMING CABLE | MAX. SETTING | MAX. FUSE RATINGS | |
---|---|---|---|---|
Size in Sq.mm, 3.5 Core | Over Load Relay | |||
in HP | CU | AL | in AMPS | |
15 | 6 | 10 | 16 | 32 |
20 | 10 | 16 | 21 | 50 |
25 | 16 | 25 | 25 | 63 |
30 | 16 | 25 | 29 | 63 |
40 | 25 | 35 | 39 | 80 |
50 | 35 | 50 | 46 | 100 |
60 | 60 | 70 | 56 | 100 |
75 | 50 | 95 | 61 | 160 |
100 | 70 | 150 | 84 | 160 |
120 | 95 | 185 | 110 | 200 |
150 | 150 | 240 | 134 | 250 |
180 | 185 | 400 | 161 | 315 |
215 | 240 | 325 or 150, (2 Run) |
191 | 400 |